Update Of Project

Here is the Initial Gantt Chart which I created at the beginning of the group project:


Due to issues within the module, we applied for an extension until the 21st of December which has since been granted. This means that we can update the Gantt Chart to accomodate this extra time so that we can use it wisely in order to achieve our full potential. Although we were not behind in this section of the module, it has meant that some of the areas we would have either pushed to have completed or had to rework to save time can now be accomplished, hopefully allowing us to achieve a higher grade. The main part of the project which has been affected is the amount of time allocated for the animations and write up. This has been extended by two weeks as this will be ample opportunity to express our animation techniques, research new techniques and tie up any loose ends.

The image below shows the new and updated Gantt Chart: